MilliporeSigma, Jaffrey, NH

PROJECT SUMMARY

In 1983, Millipore Corporation hired Hutter Construction Corporation to be their Construction Manager-at-Risk for their Main Office and Manufacturing Addition and Renovation project in Jaffrey, NH.

Since that project was completed we have served Millipore repeatedly over the years as they have expanded, modified and refitted their facility to the ever-changing demands of their marketplace. To date, Hutter has successfully completed 142 construction and service projects for MilliporeSigma.

The following is a list of some of the larger projects we have completed at the Jaffrey plant:

1983: Main Office/Manufacturing Add/Reno – $3,433,000
1986 – 1988 Sewer Main Upgrade/Misc. Repairs – $250,000
1989: Molding Renovations – $295,000
1990: Water Reclaim Tank Supports – $340,000
1991: PFA – $300,000
2000: Hollow Fiber Manufacturing – $390,000
2004: Pre-Filter Cleanroom – $692,710
2004: Warehouse Addition – $4,500,706
2005: Warehouse Roof Reinforcement – $359,419
2005: Parking Lot Expansion – $203,807
2005: Pilot Molding Area – $139,767
2005: Building “L” Transfer Cleanroom – $4,711,933
2006: DCM Recovery – $1,653,975
2006: Durapore Water Room – $163,191
2006: Durapore Renovations – $328,583
2007: Express Cleanroom – $774,298
2008: Cafeteria Renovation – $176,111
2012: Viresolve Clean Room Relocation – $1,211,009
2012: DCM Scrubber Upgrade – $251,540
2012: Durapore Clean Room Expansion – $849,469
2012: Wastewater Treatment Plant Equalization System – $1,969,059
2012: Engineering Office – $130,090
2015: Front Parking Expansion – $134,471
2015: Chemical Storage Building – $194,500
2016: DSP Facilitation – $1,219,700
2016: Switchboard Replacement 1 & 2 – $748,000
2017: DMSO Discharge – $466,496
2018: Pellicon 3 Relocation – $1,199,000
2018: Durapore Consolidation Facilitation – $410,000
2018: Pellicon 3 Chiller Expansion – $1,125,384
2019: Modular Clean Room – $182,681
2020: V-Pro Phase 2 – $845,581
2020: Lab Expansion Site Electrical – $291,000
2020: Capacity & Lab Expansion – $15,319,880

 

MilliporeSigma, Jaffrey, NH
MilliporeSigma, Jaffrey, NH
MilliporeSigma, Jaffrey, NH
MilliporeSigma, Jaffrey, NH
MilliporeSigma, Jaffrey, NH

IN PROGRESS

%

Percent Complete

PROJECT TYPE
Industrial
Additions & Renovations

DATES
1983 through Today

OWNER
EMD MilliporeSigma Corporation

DESIGN FIRM
Avid Engineers

CURRENT PROJECT MANAGER
Owen Bertram

CURRENT PROJECT SUPERINTENDENT
Various, incl. Les Somero